Sanitation

SANTIAGO TREATMENT PLANT

Santiago del Estero, Argentina

The basic project consists of the rehabilitation of an existing pump station to pump new flow through the main sewer, pushing the liquids through a new pipeline to the treatment effluent plant which is of the » Activated sludge and anaerobic sludge digestion» type.

The work will benefit more than 250,000 inhabitants of the Santiago del Estero province and ensure the environmental care of the Rio Dulce

4.083 m

Pipe Line

117.791 m3

Earthworks

7.245 m3

Reinforced concrete

250.000

Benefitting population

PROJECT

Retrofitting Pumping Plant Construction Drive and Effluent Treatment at the Santiago del Estero Station.

CLIENT

U.C.P. y P.F.E. -Unidad de Coordinación de Programas y Proyectos con Financiamiento Externo del Ministerio de Planificación Federal, Inversión Pública y Servicios.

DESCRIPTION OF WORKS

The basic project consists of rehabilitating an existing pump station to pump new liquid flow through the main sewer, pushing the liquids through a new pipeline to the treatment effluent plant. Once treated, the liquids are destined for the Dulce river via discharge into the Viano channel adjacent to the plant. The first construction stage plant consists of two processing modules each of 27,000 m3 / day, making a total of 54,000 m3 / day.

Movimiento de suelos:

Earthworks

Fillers with selected soil 40,193 m3

Excavation in plant area 51,128 m3

Excavation and fillers 26,470 m3

Drive pipe diameter 1200 mm 4083 m

Reinforced concrete H-30 7.245 m3