dehydrated gas transportation
Laguna de Oro Pipeline – Boleadoras, Province of Santa Cruz
Petrobras Energía S.A. (Santa Cruz 1)
The project involved laying a gas pipeline of 15.2 km long and 16″ in diameter, readjusting an oil pipeline of 6″ and additional facilities.
A pipeline designed to carry gas production from the fields in La Paz and La Porfiada to the Boleadoras Gas Treatment Plant.
It is designed to carry 4 million m3 / day of dehydrated gas operating at 60 bar and the course lies parallel to an exiting 6″ pipeline.
Work, in addition to laying the pipeline, involved the installation and commissioning of a 16 inch scrappers launch, a scrappers receiver of equal diameter and a biphasic gas separator.
The work on the oil pipeline included the installation and commissioning of a 16 inch scrappers launch, a scrappers receiver of equal diameter and a biphasic gas separat